Nevskaya Ratusha administrative and public center with underground parking, Saint-Petersburg, Russia with the total area of 100 736 sq m

17th August 2013 the Saint Petersburg vice-governor, Marat M. Oganesyan, who is in charge of urban development and construction, visited the project site with general inspection of the current works going on Administrative building and specifically glass installation of the Dome. Vice-governor has been satisfied with the progress of works. Velko-2000 project team is doing their best to deliver the project façade scope by the end of this year as planned.

Current progress of work on site:

  • The installation of unitized façade with natural stone on 3-8 floors of Administrative building has been completed in full on the facades facing Degtyarny pereulok and along Moiseenko St, 85% completed on the façade facing Novgorodskaya Str. And 90% on the Main façade; the natural stone semi columns are currently being mounted on three building fronts; the glazing works have been commenced on 1-2 floors.
  • Glazed curtain walls of Administrative bldg courtyards are currently under structural silicone sealing.
  • On the Dome the installation of glass infill has been commenced and is in rapid progress.
  • On all 4 facades of Business Center-2 the installation of ventilated façade with natural stone is going ahead; mounting of stone cornices are under completion; the installation of louvers is going on the roof tech floor.
  • On Business Center-3 the installation of ventilated façade with natural stone and double skin glazing on 3-10 floors and columns of the Gallery has been completed. As of today installation of natural stone elements of the Gallery are under completion.

Multifunctional residential area with Trud stadium restore on Mytnaya Str, Moscow with the total area of 61 000 sq m

  • On the balcony area of bldg 2 installation of ventilated facade is currently running;
  • The metal abutments are under installation on blds 3,4;
  • On bld 6 mullion-transom façade with glass infill has been completed on areas 2.4,1.5,1.3,1.2, 2.5; the glass and fibre cement infill have been inserted on the area 2.5; fixing of pressure plates and decorative caps has been 90% completed. The installation of fire rated spandrel panels, BMU tracks is currently running. Installation of parapet coping has been 80% executed; corner elements on basement area are being mounted.

Eurasia Tower, plot 12 Moscow-City MIBC, Moscow, with the total area of 74 000 sq m

  • The installation of unitized transparent façade is going ahead on the “tooth” area, projecting area of the tower;
  • Steel columns are being mounted on 71-74 floors as well as on the 1st floor of the top part;
  • As of today the mounting of mullion transom framing is going ahead on the 1st floor of the top, the central area have been completed in full, the glass insertion has been commenced;
  • On the Gallery the installation of shadow boxes, insulation and glass units is under completion;
  • On the Podium curtain wall area the mullion-transom facade is currently being mounted.

Nevskaya Ratusha administrative and public center with underground parking, Saint-Petersburg, Russia with the total area of 100 736 sq m


Multifunctional residential area with Trud stadium restore on Mytnaya Str, Moscow with the total area of 61 000 sq m


Eurasia Tower, plot 12 Moscow-City MIBC, Moscow, with the total area of 74 000 sq m