Nevskaya Ratusha administrative and public center with underground parking, Saint-Petersburg, Russia with the total area of 100 736 sq m

  • The installation of unitized façade with natural stone on 3-8 floors of Administrative building: completed in full on the Main façade and the facade facing Degtyarny pereulok, 95% of façade have been installed along Moiseenko St; preliminary work is going ahead on the façade facing Novgorodskaya Str.
  • Glazing of the drum area of Administrative building courtyards is 90% completed.
  • In the atrium area of Administrative building the steel support structures of the dome, lift shaft, terrace and TV-studio have been installed in full scope, as well as preliminary drilling works on fixing aluminium framework brackets are being carried out on the dome area.
  • On Business Center-2 installation of ventilated façade with natural stone is running on the main and end facades, preliminary installation works are being carried out on the other two ones; insulation fixing is 80% completed on the roof engineering floor and at the moment the installation of louvers substructure is going on.
  • On Business Center-3 the installation of ventilated façade with natural stone has been completed in full at the area of 3-10 floors, the installation o f Gallery columns has been commenced.

Multifunctional residential area with Trud stadium restore on Mytnaya Str, Moscow with the total area of 61 000 sq m

  • On the balcony area of bldg 2 installation of ventilated facade is going ahead: on bldgs 3 and 4 the balconies have been closed in full scope; on the roof area of bldg 4 the installation of brackets for building maintenance system is carried out, on bldg 1 and 2 the brackets have been fixed in overall.
  • The installation of fire rated spandrel panels and 2-5 floor glazing is currently running on building 6. On the roof area of building 6 the parapets and tracks for BMU are being mounted.

Eurasia Tower, plot 12 Moscow-City MIBC, Moscow, with the total area of 74 000 sq m

  • The installation of unitized transparent façade is going ahead on the “tooth” area, projecting tech area of the tower;
  • The mounting of steel outrigger beams is currently under completion on 49 floor;
  • On the Podium area the installation of insulation, wall brackets and guiding profile of ventilated façade is going ahead;
  • The installation of mullion-transom façade of the gallery has been commenced.

Nevskaya Ratusha administrative and public center with underground parking, Saint-Petersburg, Russia with the total area of 100 736 sq m


Multifunctional residential area with Trud stadium restore on Mytnaya Str, Moscow with the total area of 61 000 sq m


Eurasia Tower, plot 12 Moscow-City MIBC, Moscow, with the total area of 74 000 sq m