Multifunctional retail center with parking area located in Moscow, 19km MKAD, bld20, blocks 1,2
-
More than 70% o f the wall brackets have been mounted;
-
Mullion-transom aluminium framing is being installed on both buildings.
VTB Arena Park, buildings 1,2 located at Lenigradskiy prospect 36, Moscow with the total façade area of 38 809 m2
-
On all the fronts of bldgs 1, 2 and on the courtyard of bldg 1 the mullion-transom aluminium framework is currently being installed;
-
Installation of metal flashings, insulation and interfaces of 1-2 floors has been 90% completed on bldg 1 and 30% completed on bldg 2;
-
On the upper floors of bldg 1 glazing works has been commenced.
Knightsbridge Private park - de luxe residential complex, located in Moscow, Kooperativnaya Str. 14/19 block 16.
-
90% of substructure for stone cladding has been installed;
-
The natural stone façade elements are currently being mounted on 1-2 floors.
Dolphinarium building located at Prospekt Mira 119, Moscow, scope of works: 13 000 m2
-
Installation of entrances has been commenced;
-
Aluminium mullion-transom framework for the roof area glass screens is currently under installation;
-
Waterproof sealing of joints is running;
-
All the opening vents have been mounted.
Multifunctional residential area with Trud stadium restoration located on Mytnaya Str, Moscow with the total area of 61 000 sq m
-
On high-rises the facade units are being mounted on technological openings to be closed after tower crane dismantling;
-
Installation of insulation and mullion-transom framing is running on the Podium.
Eurasia Tower, plot 12 Moscow-City MIBC, Moscow, with the total area of 74 000 sq m
The stepped glazing area is installed in full;
Installation of natural stone louvers is under completion on Podium area; rain screen facade with STL steel cladding panels, doors and flashings are being mounted;
On the sloped parts of Gallery the stone cladding has been executed in full, structural glazing is under installation;
Door systems of the Gallery have been all installed, execution of interfaces is under completion;
On the main tower building the installation of decorative upright bars is being finalized.
Crown structure on Evolution Tower, Moscow-City MIBC, plot 2-3
-
Installation of one main arch steel structure is running and all the other steel elements of the arches and trussing ribbons are being supplied;
-
Embedded items for architectural lightning are being mounte;
Nevskaya Ratusha administrative and public center with underground parking, Saint-Petersburg, Russia with the total area of 100 736 sq m
Administrative building
-
Installation of corner semi-columns on the Moiseenko façade and semi-columns of 1-2 floors on Novgorodskaya is under completion;
-
On the Novgorodskaya façade the entrances’ soffit cladding works have been completed;
-
The side elements of the natural stone Emblem of the Main façade have been installed;
-
The temporary platform erected on the Dome base for installation purposes is being dismantled;
-
Atrium glazing is under completion;
-
Terrace STL steel portals sheeting is being adjusted;
-
On A, B courtyards louvers installation and glass replacement are being completed; C, D courtyards have been glazed in full.